Sandbag Sand Calculator (Metric)

Estimate sand tonnage, storage volume, and truckloads for sandbag operations.

Inputs

Total target stock (e.g., 100,000).
Typical operational fill is 15–20 kg; 18 kg is common.
Dry washed sand ≈ 1.55–1.65 t/m³ (default 1.60).
Tandem tipper typically 10–12 t; set your fleet norm.
Water content adds mass during handling (e.g., 5%).
Spillage, shrinkage, overfill margins (e.g., 5–10%).
Quick set:

Results

Total sand mass (t)
Storage volume (m³)
Estimated truckloads (loads)
Assumptions & formulae
  • Base mass (t) = bags × (kg per bag) / 1000
  • Adjusted mass (t) = Base × (1 + moisture%) × (1 + contingency%)
  • Volume (m³) = Adjusted mass / bulk density (t/m³)
  • Truckloads = Adjusted mass / truck capacity (t)

Typical planning ranges (FYI)

For 100,000 bags at 18 kg each, dry density 1.6 t/m³: expect ≈ 1,800 t sand (≈ 1,125 m³), plus allowances — practical procurement target ≈ ~2,000 t including moisture and wastage.